Meeting Minutes — Add Comment
13
Mar 12
Start: 7:06pm
Members: Anurag, Akshat, Joshua Yuan, Raphael, Brent, Matt, Nikunj, Eva, Ali, David, Michelle
Mentors: Mr. G, Mr. Lowd, Mr. Lomazov, Ms. Chu, Ms. Yang, Fernando, Mr. Kanaris
Officers: Alric, Annie, Diane, Miles, Vincent, Eric, Brianm, Aneesh, Michael L, Lucy
Active Member Meeting Minutes – March 13, 2012
Lynbrook Robotics FIRST Team#846
Start Time: 7:00 PM This Agenda is closed to editing at 6:30pm.
Download the Encrypted Manual!
-
- http://www.usfirst.org/roboticsprograms/frc/competition-manual-and-related-documents?id=452
- svn checkout http://frc2012-gamedocs.googlecode.com/svn/trunk/ frc2012-gamedocs-read-only
SVN version maintained by D.Giandomenico (trial effort)
Officer Reports
Treasurer; Secretary;
Notes: DRI = Directly Responsible Individual
Old Business
- Mr. Lowd and Ms. Eva interesting facts/story [DRI: Mr. Lowd] (7:06pm)
- Sweaters [DRI: Alric] (7:13pm)
- Processing / Shipping
- still waiting, waiting on confirmation of order
- May get them left Next week.
- T shirts [DRI: Alric] (7:14)
- Processing / Shipping. Distribute Monday, Tuesday, Wednesday.
- Received them on Friday Night
- Distributing them for the entire week (at the library)
- Wednesday; 3-14-2012 will be distributed in room 608 lunch meeting
- Medals not distributed. [DRI: Alric] (7:13)
- 3 from last year (4 total)
- 1 went to Miles
- 1 went to other member
- Newsletter [DRI Vincent] (7:15)
- have a rough draft
- need pictures from the hard drive
- need to review/edit the articles a little more
- may not be able to bring one to NYC?
- Photo Journal [DRI: Eric] ()
- Discuss after meeting
- Plan for NYC
- print a PDF file at Kinkos or at Alric’s fathers house
- binding [Alric] – just use cover sheets?
- spiral bound?
- Bring Last year’s photo journal
- order one at competition to get one by SVR
- Add a team picture?
- main objective:
- something to let the judges look at
- captions are important
- need to make sure everything is accurate
- NYC Regional (7:29pm)
- go over logistics, double check everything is fine
- Rides [DRI: Annie]
- sent out a form for members to respond/sign up
- need to confirm
- Mr. G needs a pick up from his house (handled by Anurag)
- Name tags [DRI: Diane]
- DONE, improved with new design
- Annie has pins from previous competition
- need people with color printers to print out a couple of pages.
- Annie Yang, Jackie, Joahua, David, Lucy
- Flying
- no frequent flyer numbers
- Packing [DRI: Michael L]
- need more help
- software people please look over electronics list
- Prepare book & visuals for judges [DRI: Alric]
- are already in place
- adding new ones to the book
- new newsletter
- 1-2 page graphic description
- Raphael: Key Detection
- Miles: Broach press, off season work, friction test
- Anurag: Design of the Tail
- Vision System, ball trajectory (Michael C.), Talking points
- Diane: Pokemon Card
- Anurag, Miles, Eric: Shooter testing
- being worked on, need to get the items printed, etc.
- Build of Materials – BOM [DRI: Mr. G]
- really tight this year, added a lot of extra expenses
- vision ($318), wheels, gear boxes, pneumatics, 9 speed controllers, 2 spike relays, 4 pneumatic controls, etc.
- Result: $3416 ($84 under budget)
- $645 to control system
- $1300 Drive train
- vision $318
- etc.
- Scouting Sheet
- asked to make a list of important things to note.
- things that could be numerically calculated, compile list of what is most important, etc.
- sent out new list/thread
- Team Dinner
- Friday, February 26, 2012
- need to get reservation Today/Tomorrow
- found nothing special, expensive dinner, budgeted 75$ per person for this (2 meals)
- have a buffer which we could move over to food (# is being calculated to Aneesh, Annie, Alric)
- Thai, Italian, Pizza
- meet after this and will find more restaurants and choices
- Tour – Circle Tour [DRI: Aneesh]
- SVR
- registering for STIMS, want everyone to go on this. list of names sent
- FLL Visit [DRI: Michael L] (8:35pm)
- No Go need to have a week notice
- Camp Galileo Demo. [DRI: Michael L] (Tabled)
- Flag [DRI: Matt] (8:37pm)
- things are ready, thank you to Mr. Harrison
- “looks really nice and very done overall!” ~ Brian Axelrod
New Business
- Senior Cords (8:38pm)
- up to club discretion
- person must ask for a cord
- those who have been to a competition and attends lunch meetings
- 2-3 People in question
- Draft up a bylaw for the team constitution.
- Plausible bylaw:
- pay membership dues and attend lunch meetings (0)
- Participating Active member should get it: have done more than and average member (fee and lunch), goes to outside school meetings/activities/classes; if majority of officers know the member. (10)
- Abstain (7)
End: 9:04
Meeting Minutes — Add Comment
10
Mar 12
Start: 7:00pm
Mentor: Mr.G, Mr. Lowd, Ms. Chu, Mr. Xie, Mr. Kanaris
Member: Tony, David, Nikunj, Raphael, Abhiram, Michael C, Anurag, Joshua, Jackie, Reo, Daniel, Matt
Officers: Brian, Jocelyn, Michael L, Miles, Eric, Robert, Diane, Lucy, Vincent
Active Member Meeting – March 6, 2012
Lynbrook Robotics FIRST Team#846
Start Time: 7:00 PM This Agenda is closed to editing at 6:30pm.
Download the Encrypted Manual!
-
- http://www.usfirst.org/roboticsprograms/frc/competition-manual-and-related-documents?id=452
- svn checkout http://frc2012-gamedocs.googlecode.com/svn/trunk/ frc2012-gamedocs-read-only
SVN version maintained by D.Giandomenico (trial effort)
Officer Reports
Treasurer; Secretary;
Notes: DRI = Directly Responsible Individual
Old Business
- Mr. Lowd’s interesting talk! [DRI: Mr. Lowd] (7:00pm)
- Sweaters [DRI: Alric] (7:02pm)4
- still processing at custom ink (1-2 weeks until we get them)
- Processing / Shipping
- T shirts [DRI: Alric] (7:05pm)
- may come worse case this Saturday
- Processing / Shipping. Distribute Monday, Tuesday, Wednesday.
- Medals not distributed. [DRI: Alric] (7:06pm)
- need to give to: Grace Deng
- Newsletter [DRI Vincent] (7:53)
- started to set up formatting on Publisher
- Want to hold meetings on Saturday and Sunday (March 10, 11)
- from 2-6 in the library
- information will be sent out
- Send out draft on Sunday Night.
- Photo Journal [DRI: Eric] (7:08pm)
- review page of names again
- review possible pictures
- feed back:
- title alignment
- spelling of Staff names
- will have an email sent out, respond if something is wrong
- NYC Regional (7:13pm)
- go over logistics, double check everything is fine
- will have rides ready – see Annie’s Email
- food: bring some snacks in your backpack, carry on bag, etc.
- bring some cash if you want to buy something to eat
- taking a bus at New York
- keep your luggage and bags with you AT ALL TIMES!
- Trip forms due Tomorrow, Wednesday (3-7-2012)
- Name tags [DRI: Diane Wang]
- currently with Alric?
- will look for them, contacting others.
- need help to format printing: Talk with Brian
- Packing next week (-dg) (DRI: Michael L)
- Prepare book & visuals for judges (-dg)
- start writing up your personal projects.
- Aesthetics (DRI: Diane)
- Bridge Test (DRI: Matt)
- Hex Broach, Prony Brake (DRI: Miles)
- process, CAD Drawings, Stress Analysis
- Ball trajectory tests (DRI: Robert)
- Key Tracker (DRIs: Tony, Raphael)
- Tail (DRI: Anurag)
- curve vs. line
- need more leverage, angle relative to the bridge, gain momentum as bridge goes down
- steel/materials: durable and slippery, (vs aluminum, more sticky), other objects to fragile
- Conveyor Belts (DRI: )
- relates back to our old robots
- learning from past experiences (2006)
- keeping belts on the conveyor
- tie wraps on a belt
- Vision test (DRI: Brian)
- pictures of differences between cameras and lighting
- Build of Materials – BOM [DRI: DG]
- going through everything we put on the robot
- add up all the costs of parts/ metals on the robot
- will need a sheet to present to the judges
- welcome to help Mr.G
- FLL Visit (after March 18, 2012 [the FLL Championships]) [DRI: Michael L] (7:09pm)
- Invite to Silicon Valley: give them tour (DRI: Michael L)
- Camp Galileo Demo. [DRI: Michael L] (7:56pm)
- Still pending
- Current Projects (7:56pm)
- robot work is going on
- test rig is done
- Flag [DRI: Matt] (7:56pm)
- use a shower pole and add finials
- Stuff: http://tinyurl.com/7hml78g
- Diane will be working with Matt; send out information within 2 days and need to decide
- need cost and top personal choices
New Business
- Robot in New Jersey! (8:05pm)
- Scouting Sheets (8:05pm) (DRI: Michael L)
- rely on papers a lot
- ran out of papers
- need to have 1 page of everything
- names from highest recommendation and reason why they are on list
- best chars (defense, offense, bridge, etc.)
- list of who will alliance with others is a bonus
- Alex is willing to help
- keep meeting in the room if you can!
End: 8:29pm
Meeting Minutes — Add Comment
10
Mar 12
Start: 10:00am
Mentor: Mr. Xie, Mr. G, Mr. Kanaris, Mr. Lowd
Members: Olivers, Akshat
Officers: Robert, Miles, Michael L
Robot Improvement Meeting – Feb 25, 2012
Lynbrook Robotics FIRST Team#846
Start Time: 10:00 AM This Agenda is closed to editing at 9:30 AM.
Only 19 days till NYC Regional!
- Download the Manual!
- http://www.usfirst.org/roboticsprograms/frc/competition-manual-and-related-documents?id=452
- svn checkout http://frc2012-gamedocs.googlecode.com/svn/trunk/ frc2012-gamedocs-read-only
SVN version maintained by D.Giandomenico (trial effort)
Notes: DRI = Directly Responsible Individual
Business
- Weight reductions (10:00am)
- motors + gearboxes (purchased)
- pneumatics (reduce brass, steel clevises etc) (DRI: Michael L)
- fit new plastic tank w/fitings
- need to abide by the given parts from FIRST
- may not be able to replace all of them with plastic fittings
- Weight Reduction ~0.2 lbs
- Can get this done before going to New York
- must assemble and pressure test
- Order the right parts
- Lighter plastic Tanks
- bigger, have two, only need one tank, may be able to run it off the compressor
- Weight reduction ~0.5 lbs
- Pressure Test, mounting area (zip ties instead of mounting brackets)
- Overall Weight Reduction for pneumatics: ~0.7 lbs
- lighter panels (DRI: Robert)
- Lighter material for parts which are not needed
- create a poly-carb “gusset” to replace the current poly-carb shelf.
- will require the use of rivets, thin poly-carb, etc.
- try to limit the amount of shaking; loss of comms may occur because of this.
- Additional Supports….
- supports from the ground
- will talk about this later
- Side plates of the conveyor (make extras just in case)
- Hopper – use less poly-carb, will have some rigidity, lightening holes, use bending techniques,
- worries: deformation, snagging hazard, etc.
- try and use 1/32 poly-carb
- adding cowlings
- Overall Weight Reduction for poly-carb: ~0.5 – 1 Lbs
- Signage (11:22am) (DRI: Diane)
- need area for sponsors
- cowlings. deflection of the material from the heat bending is weird. take a look
- Driver practice (11:23am) (DRI: Robert)
- repair gearbox
- roll pin and a bearing
- need to get materials.
- find out why it failed
- NASA Ames
- when we get something up and running we are invited to NASA
- drive, alignment, camera, autonomous, core parameters
- Date: Friday; March 2, 2012
- Test: Saturday; March 3, 2012
- Gearbox shifter (11:33am) (DRI: Miles)
- Ideas to improve: reduce overall force, by reducing pressure, or smaller diameter actuators
- Actuator does not have full contact with the shifter shaft.
- no easy solution.
- put a bungee cord.
- cushions, washers, thrust washers
- Protect bearings by limiters
- may not be effective
- redesign shift block / bearing assembly (e.g. cam follower in slot)
- add gear-speed matching software for faster shifting
- Will have spares during competition
- Shooter
- surface modifications
- Collector
- needed?
- Hopper objectives (10:51am) (DRI: Mr. Xie)
- Primary Objective (in order of priority)
- human loading
- human loadable – low 32″ front entry
- robot loadable – higher backboard; large opening
- Ideas
- tilt the hopper and have a flange (~3 in). could put sponsors on it. looks weird
- need to have a test.
- take ball vertically and drop on ramp
- Add a bungee cord for. Aluminum vs. Bungee. Weight vs. Structure
- have a 2nd opening for the hopper. Do not hit the bridge.
- Diane – Art, sponsors
- Mr. Xie, Alric – Design work
- Bridge depressor: perfect – no changes needed!
- Robot shipping schedule – still unknown (DRI: Abhishek Johri)
End:
Meeting Minutes — Add Comment
10
Mar 12
Start: 7:03pm
Member: Eva, Mishan, Brent, Raphael, Rishabh, Akshat, Anurag, Aurea, Abhiram, MAtt, Nikunj, Reo, Tony, Jackie, Angela, Daniel
Officers: Alric, Annie, Michael L, Eric, Vincent, Lucy, Miles, Jocelyn, Aneesh, Robert, Brian, Diane
Mentor: Mr. G, Mr. Lowd, Mr Harrison, Mr. Lomazov, Fernando
Member Meeting – Feb 14, 2012
Lynbrook Robotics FIRST Team#846
Start Time: 7:00 PM This Agenda is closed to editing at 6:30pm.
Only 35 days till Stop Build Day
- Download the Encrypted Manual!
- http://www.usfirst.org/roboticsprograms/frc/competition-manual-and-related-documents?id=452
- svn checkout http://frc2012-gamedocs.googlecode.com/svn/trunk/ frc2012-gamedocs-read-only
SVN version maintained by D.Giandomenico (trial effort)
Officer Reports
Treasurer; Secretary;
Notes: DRI = Directly Responsible Individual
Old Business
- Mr. Lowd’s talk (7:03pm)
- Sweaters [DRI: Alric] (7:05pm)
- Arriving on Friday!
-
T shirts [DRI: Alric] (7:05pm)
- Spreadsheet will be sent out
- Need students and mentor sizes
- Need to be in by this week
- getting money from the room, need to get someone to do this
- changes: sponsors, year
- cost = $25
-
Flag [DRI: Eva] (7:07pm)
- ordered coming in sometime next week
-
Newsletter [DRI Vincent] (7:07pm)
- need to get members to write about their experience (2)
- deadline to finish:
-
Awards (7:08pm)
-
Entrepreneurship [DRI: Diane]
- is not a submission
- bring to the event, have pit interview
- have a formal submission
- revising the submission
- will present to team next week
-
Woodie Flowers [DRI: Annie]
- done, checking is going to be done by a literature teacher
- changes will be made and word count will be taken in for consideration
- which regional are we going to submit
- submit to SVR
- Need information from a FIRST affliate
- name and email
- will be taken care of
-
Website [DRI: Michael L]
-
Changes [DRI: Vincent Yao]
- need a page on scrips
- need to take off outdated information
- media links are not placed yet
- no pictures in 2012, get some in there
- need to submit the award – taken care of by Vincent Yao
-
Chairman’s [DRI: Jocelyn]
- shared by Alric
- on a google document
- Comments:
- missing calgames (add)
- fact- news letter = 4 pages
- instead of referring to the team (make it we; our team),
- they know what build season is, expand on why having a room is important (allow more students to actively participate)
- WRRF – emphasize it more (where, what, when [travel hour and half -> Vallejo]),
- specifics are valuable
- raised ~$45,000 for teams in our district area (one school were able to start a team with that money)
- do not convince sponsors
- kick off
- what is significant about Fremont (invite Fremont and Prospect), helped get Prospect get started
- what are we doing to get more people involved in engineering
- FIRST Lego League
- president founded X-bots
- helped out at least 3-4 teams
- Lego Bionic Fusion, X-Bots
- 4 members working with 2 different teams
- meetings with parents to introduce the program
- both teams ranked high/are champs
- Held a library summer camp
- 3 members
- Botball
- Night in the Quad
- not priority
- invite other members from other teams who were unable to continue with their own teams
- 2 members (Mishan, Annie)
- fleet week
- vex robot with the NASA team to children attending the 2 day event in San Francisco
- Future Star Program
- taught low income students how to make a robot
- Classes
- AutoCAD ~ 50 members attended
- six, 4 hour sessions
- Software
- student created CD bot to teach members
- Miller Robotics club run by Co-President Alric Siu
- display of the old robot
- Demonstrations to schools and companies
- promote robotics
- with these workshops Cupertino’s teams were founded
- Flowed well, well written, remember what the Chairman’s award is all about (encouraging Science, Business, Technology Math, Engineering within our school district)
- Need to Finish and submit by Wednesday February 15,2012
-
Video [DRI: Michelle, Christina] <– cannot attend meeting today
Basic filming is done; scheduled interviews are done; This week we will continue to compile the video base.
- working on it, have most of the interviews they need, more film needed on the room, etc.
- Due Date: Bring things to the competition
- Blurbs [DRI: Eva]
- some to be reviewed/changed
- will be finished
- Due: Thursday Morning at 9AM
-
Photo Journal [DRI: Eric] (7:16pm)
- information will be sent out through email for others to review what we have so far
- pictures, names
- will have a separate meeting for photo journal
- will have a draft by next week
- needs to get ordered by the end of February; order on February 25, 2012; arrive on March 10, 2012
- help: Reo, Aneesh, Michael L, Matt,
-
NYC Regional Details (7:50)
- school information (submitted by Mr. G)
- names of members, Room Assignments, etc.
- need permission forms (medical, etc.)
- put a page on the website that allow students to complete and print out: Robert will head
-
Parent Night
- Date: 2 weeks before the actual trip (February 28, 2012 room 608 at 7:00pm)
- headed by Co-presidents
- Itinerary
- headed by Co-presidents
-
A FLL (Lego Bionic Fusion) team visit [DRI: Michael Lin] (7:56)
-
- have not gotten a response back yet, still trying to plan meeting on a weekday
New Business
- CalGames bid [DRI: ???] (756)
- hosting CalGames
- Believe that we should do it
- paid off a lot, spread awareness to the school
- willing to put the time in
- will have hosting duties
- need parent help
- tasks
- need parent help
- concessions
- signs
- maps
- Anurag, Rishabh, Nikunj, Reo
- For: 23 Against: 0 Abstain: 1
- Requested to go to NASA [DRI: Brian]
- get there first thing in the morning
- Transportation will be taken care of
- only allowed to get 4 students and 2 mentors
- 2 mentors:
- Members:
- Hardware
- Akshat, Anurag,
- Software
- Robert may not be able to go the entire time
- students may not drive onto the base
- No Mechanical work at all
End: 8:07pm